MIL-DTL-62267B(AT)
4.5.4.18.3 Operator's seat test. To determine conformance to 3.4.18.3, with an average
weight person (180 lbs (80 kg) nominal) in the seat, force required to actuate adjustment lever
shall be measured and shall not exceed requirement.
4.5.4.18.4 Fuel shut-off test. To determine fine conformance to 3.4.18.4, the engine shall be
operated at 50% of governed rpm, manual shut-off valve shall be actuated to "off" position. Time
required for engine to stop shall be measured and shall not exceed requirement.
CAUTION: Fuel valve shall be returned to "ON" position and the system primed and
bled of air.
4.5.4.19 Fire extinguisher. To determine conformance to 3.4.19, the fire extinguisher
shall be tested for operation. With the engine idling at 700 to 800 rpm, the internal control shall
be pulled with a maximum effort of 55 lbs (25 kg) using a force gauge. The first shot shall
actuate one bottle. After a time delay of more than 6 seconds but less than 11 seconds, the engine
shall have stopped and the system shall begin discharging CO2 into the engine compartment and in
the center of the engine "V". After returning the handle to its original position, a second
actuation shall discharge the remaining two bottles of CO2. Removal and weighing of each CO2
bottle after test shall show a minimum of 9 lbs (4 kg) of CO2 discharged during test.
CAUTION: When conducting these tests, safety precautions shall be exercised
(see 6.3.1).
4.5.4.20 Personnel heater test. To determine conformance to 3.4.20 and 3.4.20.1, the
heater shall be started and observed for proper operation and tested for conformance to all
requirements.
4.5.4.21 Engine smoke generator test. To determine conformance to 3.4.21, activate the
engine smoke generator switch when the engine is warm and operating at 1600 rpm. Verify that
both right and left exhaust ducts emit white smoke.
NOTE: Do not test the engine smoke generator for more than 15 seconds, nor within a
building, nor with personnel exposed to the exhaust plume.
4.5.4.21.1 Smoke grenade discharger circuits tests.
4.5.4.21.1.1 Arming test. To determine conformance to 3.4.21.1.1, operate the master
battery switch to ON and the grenade system power switch to ON, and verify that the power-on
(ready) lamp in the grenade power box illuminates. Operate the grenade system power switch to
OFF and verify that the power-on (ready) lamp is extinguished.
17